Sources:
Serial # | Date | Subject | Sources |
---|---|---|---|
69-PA-T-1A | Jan 7 1969 | Let's move the recovery force a little | 5 |
69-PA-T-2A | Jan 10 1969 | Some decisions regarding lunar landmark tracking on the F and G missions | 1, 2, 5 |
69-PA-T-3A | Jan 14 1969 | Operations required for communication loss on F and G are sure better than on C' | 1, 2, 5 |
69-PA-T-4A | Jan 14 1969 | F and G cis-lunar midcourse correction scheduling | 1, 2, 5 |
69-PA-T-5A | Jan 14 1969 | Procedures for LM aborts immediately after landing are terrible! | 5 |
69-PA-T-6A | Jan 14 1969 | D Rendezvous Mission Techniques | 5 |
69-PA-T-8A | Jan 15 1969 | F and G Lunar Orbital operations - mostly pre-DOI LM activation stuff | 1, 2, 5 |
69-PA-T-10A | Jan 21 1969 | F and G mission cis-lunar and abort plan | 1, 2, 5 |
69-PA-T-11A | Jan 21 1969 | D Rendezvous Mission Techniques Meeting - January 20, 1969 | 5 |
69-PA-T-?? | Feb ? 1969 | (unreadable) | 5 |
69-PA-T-14A | Feb 5 1969 | Two-stage LOI looks good after C' | 1, 2, 5 |
69-PA-T-15A (?) | Feb ? 1969 | (unreadable) | 5 |
69-PA-T-17A | Feb 6 1969 | MCC-H Ascent Monitoring | 5 |
69-PA-T-18A | Feb 6 1969 | F/G cis-lunar midcourse correction mission techniques | 1, 2, 5 |
69-PA-T-19A | Feb 6 1969 | Apollo Mission Techniques Documentation Schedule | 5 |
69-PA-T-22A | Feb 11 1969 | G Lunar Surface Phase Mission Techniques | 1, 2 |
69-PA-T-23A | Feb 11 1969 | F/G Mission Techniques - except for the lunar orbit phase - are ready to eat | 1, 2, 5 |
69-PA-T-24A | Feb 11 1969 | F/G Rendezvous Mission Techniques - mostly F | 1, 2, 5 |
69-FM-T-27 | Feb 19 1969 | Apollo spacecraft computer program newsletter | 5 |
69-PA-T-27A | Feb 19 1969 | All about F APS burn to depletion and landmark tracking | 1, 5 |
69-PA-T-28A | Feb 20 1969 | Descent Abort Mission Techniques | 1, 2, 5 |
69-PA-T-29A | Feb 25 1969 | Mission D Maneuver Monitoring Document | 5 |
69-FM-T-30 | Feb 20 1969 | Results of the February 18 Apollo Spacecraft Software Configuration Control Board (ASSCCB) meeting | 2, 5 |
69-PA-T-31A | Feb 24 1969 | Let's have no unscheduled water dumps on the F mission | 1, 2, 5 |
69-PA-T-32A | Feb 24 1969 | Some things about MSFN orbit determination | 1, 2, 5 |
69-PA-T-34A | Feb 25 1969 | D Mission LM PGNCS IMU drift checks | 2 |
69-PA-T-35A | Feb 26 1969 | F/G Mirror Image Targeting shall use a three-minute delay | 1, 2, 5 |
69-PA-T-36A | Feb 26 1969 | Review of the Launch Phase Abort Mission Techniques Document for Missions F and G | 2, 5 |
69-PA-T-37A | Feb 27 1969 | Some more trivia for the F mission | 1, 2, 5 |
69-PA-T-39A | Feb 28 1969 | Some MPAD work needed for the G mission | 2, 5 |
69-PA-T-40A | Feb 28 1969 | There will be no VHF ranging data collected while tracking the LM on the lunar surface | 1, 2, 5 |
69-PA-T-42A | Mar 7 1969 | G Lunar Surface stuff is still incomplete | 1, 2, 5 |
69-PA-T-44A | Mar 14 1969 | Happiness is having plenty of hydrogen | 1, 2, 5 |
69-PA-T-45A | Mar 12 1969 | Simplification to the pre-PDI abort procedure | 1, 2, 5 |
69-PA-T-47A | Mar 20 1969 | F mission lunar orbit attitude sequence | 1 |
69-PA-T-52A | Apr 1 1969 | PGNCS operations while on the lunar surface | 1, 2, 5 |
69-PA-T-53A | Apr 3 1969 | Some G Mission Techniques action items | 2, 5 |
69-PA-T-54A | Apr 4 1969 | RLS Determination | 1, 2, 5 |
69-PA-T-55A | Apr 4 1969 | AGS alignments in lunar orbit and operations on the lunar surface | 1, 2, 5 |
69-PA-T-56A | Apr 8 1969 | Some things about Ascent from the moon | 1, 2, 5 |
69-PA-T-58A | Apr 10 1969 | Descent monitoring at MCC | 2, 5 |
69-PA-T-59A | Apr 11 1969 | F Rendezvous Mission Techniques Clean-up | 1, 5 |
69-PA-T-61A | Apr 15 1969 | Let's drop one of the lunar surface RR tests | 1, 2, 5 |
69-PA-T-62A | Apr 23 1969 | F mission rule regarding DPS gimbal drive failure indication | 2, 5 |
69-PA-T-63A | Apr 15 1969 | Some things about Descent | 2, 5 |
69-PA-T-64A | Apr 16 1969 | How the MSFN and sextant data are used to target DOI and Descent | 1, 2, 5 |
69-PA-T-66A | Apr 30 1969 | What's descent al about? | 5 |
69-PA-T-67A | May 1 1969 | Descent Aborts and subsequent Rendezvous Mission Techniques | 1, 5 |
69-PA-T-69A | May 2 1969 | CSM rendezvous navigation works fine using just VHF ranging | 2, 5 |
69-PA-T-70A | May 5 1969 | Descent Monitoring Mission Techniques - a status report | 1, 2, 5 |
69-PA-T-71A | May 6 1969 | Ascent newsletter | 1, 2, 5 |
69-PA-T-72A | May 6 1969 | Comments on IMU compensation procedures | 2, 5 |
69-PA-T-73A | May 7 1969 | Apollo Mission Techniques Documentation Schedule | 5 |
69-PA-T-74A | May 8 1969 | The LM4 RR/LGC interface may be broken, but that's okay - sorta | 2, 5 |
69-PA-T-75A | May 12 1969 | Cis-lunar state vector updating procedure change | 2, 5 |
69-PA-T-76A | May 12 1969 | G mission lunar descent is uphill - all the way | 1, 2 |
69-PA-T-77A | May 12 1969 | Manual Steering for LM Ascent | 1, 2, 5 |
69-PA-T-78A | May 15 1969 | Some "improvements" in the Descent preparation procedures | 1, 2, 5 |
69-PA-T-81A | May 26 1969 | Attention worthy Descent Program Anomaly | 5 |
69-PA-T-82A | May 28 1969 | Descent, Lunar Surface, and Ascent Mission Techniques with the H crew | 1, 2, 5 |
69-PA-T-83A | May 29 1969 | DPS low level propellant light | 2, 5 |
69-PA-T-84A | Jun 4 1969 | G Rendezvous Navigation OJT is proposed | 2, 5 |
69-PA-T-87A | Jun 5 1969 | PRN ranging in lunar orbit is unnecessary | 2, 5 |
69-PA-T-92A | Jun 11 1969 | CSM Rescue Mission Techniques are complete and clean | 2, 5 |
69-PA-T-93A | Jun 13 1969 | Some significant LUMINARY program changes you should know about | 1, 2, 5 |
69-PA-T-94A | Jun 19 1969 | Ascent with busted guidance and control systems | 1, 2 |
69-PA-T-95A | Jun 24 1969 | Post Insertion CSM P52 is optional | 1, 2 |
69-PA-T-101A | Jul 1 1969 | Post-insertion alignment is lower priority than rendezvous navigation | 1, 2 |
69-PA-T-102A | Jul 1 1969 | New DPS GDA Descent mission rule is imminent if not now | 2 |
69-PA-T-103A | Jul 3 1969 | Some new ideas on how to use the AGS during Descent | 1, 2 |
69-PA-T-104A | Jul 7 1969 | Manual Ascent revisited | 1, 2 |
69-PA-T-105A | Jul 10 1969 | Tweak burns | 1, 2 |
69-PA-T-106A | Jul 11 1969 | Descent Data Select procedures are finalized | 1, 2 |
69-PA-T-109A | Jul 14 1969 | How we will handle the effect of mascons on the LM lunar surface gravity alignments | 1, 2 |
69-PA-T-111A | Jul 16 1969 | Change in delayed PDI Descent targeting procedures | 1, 2 |
69-PA-T-112A | Jul 17 1969 | Gyro calibration and accelerometer bias update and redline values | 1, 2 |
69-PA-T-114A | Aug 1 1969 | How to land next to a Surveyor - a short novel for do-it-yourselfers | 2 |
69-PA-T-116A | Aug 29 1969 | A lengthy status report on lunar point landing including some remarks about CSM DOI | 2 |
69-PA-T-117A | Sep 1 1969 | Notice of a catch-all Apollo 12 Mission Techniques meeting | 2 |
69-PA-T-118A | Sep 12 1969 | Invitation to an Apollo 13 Lunar Orbit Mission Techniques meeting | 2 |
69-PA-T-119A | Sep 16 1969 | We don't have to change LUMINARY much for point landing but there's gold in them hillsf | 2 |
69-PA-T-122A | Sep 24 1969 | Apollo 12 Mission Techniques | 2 |
69-PA-T-123A | Sep 29 1969 | Status report on Apollo 13 Mission Techniques - or "Go for CSM DOI' | 2 |
69-PA-T-129A | Oct 20 1969 | What can be done about the AOT? | 2 |
69-PA-T-130A | Oct 21 1969 | Let's hear it for "Delta Guidance"! | 2 |
69-FM-T-131 | Oct 21 1969 | Apollo Spacecraft Software Configuration Control Board meeting number 32 | 2 |
69-PA-T-132A | Oct 21 1969 | Apollo 12 Newsletter | 2 |
69-PA-T-133A | Oct 29 1969 | Spacecraft separation procedures | 2 |
69-PA-T-134A | Oct 29 1969 | Don't turn off the landing radar | 2 |
69-PA-T-138A | Oct 29 1969 | Automatic CSM Rendezvous | 2 |
69-PA-T-139A | Oct 29 1969 | AGS licks PGNCS for RCS Insertion | 2 |
69-PA-T-142A | Nov 4 1969 | Apollo 12 Descent - Final comments | 2 |
69-PA-T-145A | Nov 17 1969 | LM high-bit rate telemetry data is not mandatory | 2 |
69-PA-T-146A | Nov 24 1969 | Apollo 13 Odds and Ends Meeting | 2 |
69-PA-T-147A | Nov 24 1969 | Rover Navigation | 2 |
69-PA-T-149A | Dec 17 1969 | Apollo 13 Mission Techniques are in good shape | 2 |
69-PA-T-148A | Dec 18 1969 | LM IMU drift checks prior to descent for Apollo 13 and up | 2 |
69-PA-T-152A | Dec 31 1969 | Can we cut 2 hours out of the Apollo rendezvous? | 2 |